Used to be engaged in plant-building and project management.
From 2015 to now, I have experienced 5 new plant projects, that increase annual production capacity of a key product by 50,000 tons per year, and help my company hold near 30% market share.
OBJECTIVE
Project manager.
Section Manager, Engineering Design Division
'Copper Foil Plant #4 (Changshu, China)'
An 18,000 tons per year plant.
Jun. 2021 to Dec. 2022 (put into production)
1. Managed a project team of 6 members, responsible for the team's performance.
2. Made a three-months extension of the building permit and avoided a-year-long reconfirming works by Buliding Permit section in China.
3. Acted as a bridge between the government and company, and made sure that plant could put into production in December, 2022.
'Copper Foil Plant #3 (Changshu, China)
An 18,000 tons per year plant.
Dec. 2020 to Jun. 2021 (put into production)
1. Managed a piping design team of 10 members, responsible for the team's performance.
2. Led my teams design the utility area and help my company reduce the cost by 2%.
3. Established the project documents of change requests and lesson learned to make sure that all experience recorded correctly.
Mechanical Engineer, Technology and Engineering Division
Assistant RD Engineer, Nuclear Fuels and Materials Division
Bachelor of Science of Mechanical Engineering.
English:TOEIC blue certificate. (765)
Chinese Native.
Taiwanese.
Piping and Equipment Design. (PDMS, AutoCAD)
Mechanical Design. (PVELIES, Solidworks)
Microsoft applications. (Word, Excel...)
Project Management:PMP license.
Used to be engaged in plant-building and project management.
From 2015 to now, I have experienced 5 new plant projects, that increase annual production capacity of a key product by 50,000 tons per year, and help my company hold near 30% market share.
OBJECTIVE
Project manager.
Section Manager, Engineering Design Division
'Copper Foil Plant #4 (Changshu, China)'
An 18,000 tons per year plant.
Jun. 2021 to Dec. 2022 (put into production)
1. Managed a project team of 6 members, responsible for the team's performance.
2. Made a three-months extension of the building permit and avoided a-year-long reconfirming works by Buliding Permit section in China.
3. Acted as a bridge between the government and company, and made sure that plant could put into production in December, 2022.
'Copper Foil Plant #3 (Changshu, China)
An 18,000 tons per year plant.
Dec. 2020 to Jun. 2021 (put into production)
1. Managed a piping design team of 10 members, responsible for the team's performance.
2. Led my teams design the utility area and help my company reduce the cost by 2%.
3. Established the project documents of change requests and lesson learned to make sure that all experience recorded correctly.
Mechanical Engineer, Technology and Engineering Division
Assistant RD Engineer, Nuclear Fuels and Materials Division
Bachelor of Science of Mechanical Engineering.
English:TOEIC blue certificate. (765)
Chinese Native.
Taiwanese.
Piping and Equipment Design. (PDMS, AutoCAD)
Mechanical Design. (PVELIES, Solidworks)
Microsoft applications. (Word, Excel...)
Project Management:PMP license.